When a device, controller or link drops off an OT network, much of the outage is noticing, finding the owner, waiting and handover. Here is what to fix first.

Modern industrial environments have a heavy reliance on the OT network - this means, more technology and more points of failure. When a process stops due to a technology failure, the conversation afterwards is usually about the fix. Which card failed, which cable, which firmware.

But pull apart the timeline of a real outage and the repair is often a smaller slice than people expect. Much of the clock runs before anyone touches a tool: noticing something is wrong, working out who owns it, waiting for the right person or vendor, and passing the problem across a shift change.

All of this time is lost productivity, and if the process stoppage is at a critical path in your site’s industrial processes, the cost of process stoppage starts adding up as soon as a device fails.

This article looks at that hidden time, what the public evidence says about it, and how to shrink it.

What the evidence says, and where it runs out

Let's be upfront: public data on OT outages is thin. We could find no public mean time to repair for control-system faults (PLC, DCS or HMI), and none for loss of OT communications or devices going offline. Treat any confident "industry average" for these with suspicion.

What does exist is a handful of useful, partial signals - combined with your own real-life data on mean time to detect and resolve technology incidents.

Controls faults take longer than mechanical ones. Guidewheel, a machine-monitoring vendor, analysed more than 14,000 downtime events across 3,000+ machines. Electrical and controls stops averaged 107 minutes per event and made up 18% of downtime, against 72 minutes for mechanical breakdowns. Guidewheel's own note on controls: "Fewer events, but harder to resolve quickly."

Repair can be only half the downtime. A 2025 peer-reviewed study in Scientific Reports broke down 50 shovel failures (25 mechanical, 25 electrical) at a copper mine. Direct repair was almost 50% of total downtime. The rest went on vehicle arrival, delays, preparation, diagnosis and testing, with about 30% of downtime coming from travel to the machine and operational delays. The authors also note that electrical faults were harder to diagnose because they lack the audible cues a mechanical failure gives. It is one site, a small sample and mining equipment rather than a control network, but it is the clearest published breakdown we found.

Restart decisions take real time. A 2021 IChemE Hazards paper on plant up-time works through representative times for getting a hydrocarbon plant back to normal after an emergency shutdown. In its examples, total recovery is three to five hours, and 30 to 60 minutes of that is simply the decision to restart. These are a consultant's representative figures, not measurements.

Averages hide the long tail. An IEEE interpretation of its reliability standard (IEEE 493) notes repair times for one equipment type ranging from 11.3 to 451 hours, and says the median is the better figure for data this skewed.

Handover is a known failure point. The UK HSE notes that many accidents have involved failed communication at shift handover, including Piper Alpha, per the Cullen Report. The US Chemical Safety Board's Texas City report found that BP had no shift turnover communication requirement for operations staff, and that a day supervisor arrived more than an hour late and did no turnover with the night shift.

The numbers are patchy, but the picture is consistent. A device going offline is a technical event; how long the outage lasts depends heavily on people, ownership and information flow.

As industrial environments become more digitised, additional monitoring tools become available to detect system and process failures. This doesn’t need to be the core purpose of the application. In the experience of OpsView, many industrial cybersecurity tools such as Claroty, Nozomi, Dragos and Armis, generate valuable cybersecurity telemetry that can equally be used for operational purposes. OpsView turns that data into faster fault resolution, contextualised to the operational processes.

Five places to win back time

None of this needs new plant hardware. It is mostly deciding things in advance.

1. Give every process area a named owner

When a remote I/O rack drops offline, the first question is usually "whose is this?" If the answer depends on who happens to be on shift, minutes turn into an hour.

Map your devices and network segments to process areas, and give each area a named owner per shift, with a deputy. The Australian Cyber Security Centre's OT principles make a related point: understanding the business context of OT is vital for assessing the impact of an outage and setting recovery priorities, and process engineers should be involved in incident plans and in recovery.

2. Alert on device and comms loss, to the owner

Many sites alarm the process well but treat a quiet device as no news, so a PLC that stops talking can go unnoticed until something downstream misbehaves.

Make comms loss an explicit alert, routed to the area owner, not just a shared screen. Keep it rationalised: ISA-18.2 guidance defines an alarm flood as 10 or more alarms in 10 minutes, and an alert nobody can act on during a flood is not helping.

3. Write down who decides a restart, and on what evidence

If the restart decision alone can take 30 to 60 minutes, that is worth attacking directly. For each process area, write a short runbook: who has authority to restart, what they need to see first, and who must be told. Uptime Institute's 2025 outage survey, which covers data centres rather than plants, found that 58% of operators who had a human-error outage named staff failing to follow procedures as a common cause. Keep runbooks short enough to follow under pressure, and make them readily accessible for everyone who needs to be involved. It’s helpful to stress-test these by running simulation tabletop exercises.

4. Get vendor access ready before you need it

Waiting for the vendor is often admin: finding the contact, approving access, getting someone up to speed. The ACSC recommends an information pack for third parties, prepared before or when they are engaged, covering points of contact, naming conventions, data sources and which tools may be used, and that these packs be exercised and kept current. Pair that with a pre-approved, secure remote access path so you are not creating an emergency “break glass” connection during a system outage.

5. Rehearse the handover

Outages do not respect shift times. Use a structured handover that covers open issues, bypasses in place and what to watch for. In a small refinery trial run by Engen with the ASM Consortium (20 operators, simulated emergencies), a checklist-based handover gave the incoming shift a 9% more accurate and complete account of the unit, for about a minute of extra time. The HSE's guidance is simple and worth adopting: face to face, two-way, verbal and written.

Measure your own outages

With no public benchmarks, your own data is the best baseline you will get. For your next few device or comms outages, record five timestamps: when it happened, when someone noticed, when the owner took it, when repair started, and when the process was back to normal. If the gaps between the first three timestamps are bigger than the repair itself, you know where to start. Add the cost of process downtime to start calculating the benefits on improving your response capabilities.

A light note on tooling

This is the problem we built OpsView around. It reads your existing tooling (via API) and assigns accountability per process block, so an offline device lands with a named owner. More at opsview.si. But the practices above work with a whiteboard and a phone tree too.

FAQ

Is there a public benchmark for how long control-system or OT comms outages take to fix?

Not that we could find, for PLC, DCS or HMI faults or for loss of OT comms. The closest public figure is vendor data putting electrical and controls stops at about 107 minutes on average. Your own records are a better baseline.

If repair is not most of the outage, what is?

In a 2025 study of 50 shovel failures at one copper mine, direct repair was about half the downtime. The rest went on reaching the machine, delays, preparation, diagnosis and testing. It is worth checking the pattern at your own plant.

Where should a site start?

Name an owner for every process area, alert on device and comms loss to that owner, write down who decides a restart and on what evidence, get vendor access ready before you need it, and rehearse the handover. Then measure each phase of your next few outages.

Sources

Questions

Is there a public benchmark for how long control-system or OT comms outages take to fix?
Not that we could find, for PLC, DCS or HMI faults or for loss of OT comms. The closest public figure is vendor data putting electrical and controls stops at about 107 minutes on average. Your own records are a better baseline.
If repair is not most of the outage, what is?
In a 2025 study of 50 shovel failures at one copper mine, direct repair was about half the downtime. The rest went on reaching the machine, delays, preparation, diagnosis and testing. It is worth checking the pattern at your own plant.
Where should a site start?
Name an owner for every process area, alert on device and comms loss to that owner, write down who decides a restart and on what evidence, get vendor access ready before you need it, and rehearse the handover. Then measure each phase of your next few outages.